Photo by Adam Fagen.
Just because it’s Labor Day weekend doesn’t mean Metro is taking off. Hope that you don’t need to ride Metro this weekend because there’s going to be some serious scheduled track work going on. In fact, every line save for the Blue and Yellow Lines will be experiencing some delays due to weekend track work.
But the Red Line is bearing the worst of it: The Bethesda and Medical Center stations will be closed, with bus shuttle service replacing trains. Here’s what else is going on this weekend, via WMATA:
Red Line
Red Line trains will operate as follows from 12:01 Saturday through closing Monday:
- Between Shady Grove and Grosvenor: every 10 minutes.
- Between Friendship Heights and Glenmont: every 10 minutes.
Stations Closed: Bethesda and Medical Center
Last Train Time Change: The last Red Line train of the night from Shady Grove to Grosvenor will depart 35 minutes earlier than normal to allow for shuttle bus connections. On Friday and Saturday nights, the last train will leave Shady Grove at 1:55 a.m. On Sunday and Monday, the last train will leave Shady Grove at 10:55 p.m.
Free shuttle buses will replace Red Line trains between Friendship Heights and Grosvenor. Shuttle buses will operate on two routes:
- Express buses will operate between Friendship Heights and Grosvenor. Add up to 25 minutes of additional travel time.
- Local buses will operate between Friendship Heights and Grosvenor, making intermediate stops at Medical Center and Bethesda. Please allow 10 minutes of travel time for each station stop.
Work Performed: Grout pad, rail tie and insulator renewal, joint elimination and communication cable replacement between Friendship Heights and Grosvenor.
Orange Line
Orange Line trains will operate every 15 minutes through system closing on Sunday. Regular weekend service on Monday.
Work Performed: Rail tie, fastener and insulator renewal between East and West Falls Church.
Green Line
Green Line trains will operate every 16 minutes through system closing on Monday.
Work Performed: Rail tie, fastener and insulator renewal between Prince George’s Plaza and Greenbelt.
Silver Line
Silver Line trains will operate every 15 minutes through system closing on Sunday to accomodate rebuilding on the Orange Line. Regular weekend service on Monday.