Originally scheduled to end in March, Metro announced today that its massive repair effort known as SafeTrack will run through June.

After taking a break for the holidays, winter weather, and inauguration, SafeTrack will resume in mid-February with a doozy of a closure: a segment of Blue line track between Rosslyn and Pentagon will be entirely shut down for more than two weeks, from February 11-28.

In March, work will move to the southern end of the Blue and Yellow lines, affecting the area between Braddock Road and Huntington/Van Dorn Street stations through April 9.

Metro plans to release dates and more information for the last three surges, which will effect parts of the Green, Orange, and Red lines, later in the year.

A separate “major maintenance effort” is scheduled on the weekend of February 4-5 that will include the complete closure of six major downtown stations and the partial closure of another two.

Once SafeTrack concludes, WMATA will continue with a “regimen of preventative maintenance.” The transit agency will continue to have additional nighttime hours to do the work, as the Metro Board recently approved cuts to late-night service for two years.

Here’s the full SafeTrack schedule:

Rosslyn – Pentagon
February 11-28

A section of the Blue Line will be shut down (no trains) between Rosslyn and Pentagon.

Blue Line trains will operate between Franconia-Springfield and Reagan National Airport only

  • Arlington Cemetery Station closed (served by buses from Pentagon)
  • Orange and Silver lines will operate normally
  • Yellow Line service between Huntington and Mt Vernon Square will operate normally
  • Yellow Line Rush+ trains will run all day between Franconia-Springfield and Greenbelt
  • Braddock Road – Huntington/Van Dorn Street Yellow Line Blue Line

Braddock Road – Huntington/Van Dorn Street
March 4-April 9

Continuous single tracking will significantly reduce Yellow and Blue line service.

March 4 through March 26

  • Continuous single tracking on the Blue and Yellow lines between Braddock Road & Huntington/Van Dorn Street
  • Blue Line trains will run every 24 minutes. All Blue Line riders should consider alternate travel options during this time.
  • Yellow Rush+ trains will not operate between Franconia-Springfield and Greenbelt.
  • Yellow Line will operate in two segments: Between Huntington and King St-Old Town every 12 minutes and Between Reagan National Airport and Mt Vernon Square every 6-12 minutes
  • Between King St-Old Town and Reagan National Airport, only Blue Line trains will operate.

March 26 through April 2

  • Continuous single tracking on the Blue Line only between King St-Old Town and Van Dorn Street.
  • Blue Line trains will run every 24 minutes. All Blue Line riders should consider alternate travel options during this time.
  • Yellow Rush+ trains will not operate between Franconia-Springfield and Greenbelt.
  • Yellow Line service to/from Huntington will operate normally.
  • Riders who normally use Van Dorn Street or Franconia-Springfield stations are encouraged to use Huntington, Eisenhower Ave or King St-Old Town instead.

April 3 through April 9

  • Continuous single tracking on the Yellow Line only between King St-Old Town and Huntington.
  • Yellow Line trains between Huntington and Mt Vernon Square/Fort Totten will operate every 24 minutes at all times. All Yellow Line riders should consider alternate travel options during this time. In particular, customers who normally use Huntington or Eisenhower Ave should consider Franconia-Springfield or Van Dorn Street stations as alternates.
  • Blue Line and Yellow Rush+ service will operate normally.

Greenbelt – College Park Green Line
April-May (Dates TBD)

  • Continuous single tracking on the Green Line between Greenbelt and College Park.
  • Service information and exact dates will be announced in early March.

Minnesota Ave – New Carrollton Orange Line
May-June (Dates TBD)

  • Continuous single tracking will significantly reduce Orange Line service
  • Service information and exact dates will be announced in early April.

Shady Grove – Twinbrook Red Line
June (Dates TBD)

  • Continuous single tracking will significantly reduce Red Line service north of Grosvenor.
  • Service information and exact dates will be announced in early May.